Bunnell Hill Construction has completed the 156-door FedEx Freight Facility in Oak Creek, WI.  We broke ground on this project on November 30th last year and completed the project on December 5th, 2018.  The project was completed among some of the most challenging weather conditions- with heavy rain and  snow throughout the build resulting in record precipitation for the area.   

The project consisted of a 109,400 SF terminal building with 17,700 SF of office space and a 14,150 SF maintenance garage guardhouse, a fuel station, lube shed, guardhouse and over 27 acres of poured concrete.  

We are very proud of this project and grateful for the continued work with FedEx Freight. 